12/12/2009
Josh has been helping me sheetrock. We finished sheetrocking the upstairs master area in 27 and a half hours.

 

12/12/2009
Upstairs master area sheetrocked and finished. Now it's time to tape and mud the joints and then texture and paint.

 

12/12/2009
Upstairs master area sheetrocked and finished. Now it's time to tape and mud the joints and then texture and paint.

 

12/30/2009
Belle is adding the second coat of mud over the taped joints. We will texture after that with a joint compand and sand mix that looks something like stucco.

 

12/30/2009
Finished the pre-slope mortar bed in the master shower. Before I spread and packed the mortar bed I first layed tar paper and stapled in metal lath. My cement mixture consisted of 4 parts sand to 1 part portland and I used a bonder agent for better adhesion and compression strength. The mortar bed sloped from 1.5" to about 3/8" to the center having about a 1/4" per foot slope. Next I will add the shower liner and put in the main mortar bed which tile will be laid on.

 

1/20/2010
Making progress on the upstairs wall texture. I came up with a mixture of 1 box heavy weight joint compound to 3/4-5 gal. bucket of masonary sand and water. I trowel it on then go back with a damp sponge and float it to give it a stucco look. It is turning out really nice.

 

2/1/2010
Rabbit built our cabinets out of maple wood and brought them from his shop in Fort Worth. Here we are installing them. He hung out for a couple of days to see some of the local sights.

 

2/1/2010
The cabinets turned out beautiful. Now all I have to do is finish them and build the concrete counter tops.

 

2/19/2010
I have spent the last couple of weeks finishing the kitchen cabinets. What a job! They are maple and very difficult to finish but I came up with a solution of cleaning the cabinets well with mineral spirits and applying a stain consisting of lacquer thinner and ZAR Dark Mahogany. Then I sealed them with a Satin based polyurethane.

 

2/19/2010
As soon as I finish the cabinets I will move back upstairs to the bathroom. The shower is ready to be tiled and I will be designing and building a custom concrete countertop. This mortar bed mixture was the same as the pre-slope minus the bonder agent. The center is about 1.7" thick and the outside perimeter is approx. 3" thick.

 

3/5/2010
Currently tiling the upstairs shower. It's turning out very nice.

 

3/10/2010
Over his spring break Matt painted while I worked on the bathroom. Bold colors but I think it's going to turn out great.

 

3/18/2010
Finished painting the bunt. Tomorrow I will finally take the tape off, clean the window, and bring the ladder down for good.

 

4/09/2010
I am now plumbing in the pipe for our propane. I'm buying 21' sections and cutting and threading each piece to fit. This was not as easy as I thought but I am now getting the hang of it. While threading I add oil after every quarter turn. It is a little tedious and slow but this is the only way to get good threads. The main pipe coming in is 3/4" and it branches into 1/2" to each fixture.

 

4/18/2010
The propane is finished with no leaks and the tank is full and holding.

 